Question: A project for improving a billing process has the following precedence relationships and activity times: a. Draw the network diagram. b. Calculate the slack for
.png)
a. Draw the network diagram.
b. Calculate the slack for each activity. Which activities are on the criticalpath?
Actvity Activity Time (weeks) Immediate Predecessor(s) 13 B, C 10 F, G
Step by Step Solution
3.42 Rating (161 Votes )
There are 3 Steps involved in it
Billing process a AON diagram b The critical path ... View full answer