Question: In Solved Problem 2, estimate the probability that the noncritical path BFG will take more than 20 weeks.

In Solved Problem 2, estimate the probability that the noncritical path B–F–G will take more than 20 weeks.


Step by Step Solution

3.36 Rating (171 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Solved Problem 2 Where T 20 weeks 55 90 45 19 weeks and the sum of ... View full answer