Question: After constructing the project network diagram in problem 5, management comes up with the following in-formation regarding how many days certain activities can be crashed
After constructing the project network diagram in problem 5, management comes up with the following in-formation regarding how many days certain activities can be crashed and at what cost
Suppose that every day the project goes on costs the company $3,500. How many days should management crash the project? What activities should it crash? What is the new project length?
NUMBER OF DAYS ACTIVITY CRASH COST ACTIVITY CAN BE CRASHED PER DAY $1,000 $2,500 $5,000 $1,000 $3,000 $2,000 3 D 3 E G 1 H 3 J 2
Step by Step Solution
3.42 Rating (174 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
436-B-M-L-S-C-M (2842).xlsx
300 KBs Excel File