Create an Activity-on-Arrow (AOA) diagram based on the following information: Task A, duration 2, no dependency Task

Question:

Create an Activity-on-Arrow (AOA) diagram based on the following information:
Task A, duration 2, no dependency
Task B, duration 4, no dependency
Task C, duration 7, no dependency
Task D, duration 5, depends on Task A
Task E, duration 3, depends on Task B and Task C
Task F, duration 8, depends on Task C
Task G, duration 10, depends on Task D and Task E
Task H, duration 4, depends on Task E
Task I, duration 7, depends on Task F
Task J, duration 12, depends on Task H and Task I