Question: Dave Fletcher was able to deter-mine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and
Dave Fletcher was able to deter-mine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activitytimes:
.png)
ACTIVITY | TIME (WEEKS) ACTNTY TIME (WEEKS)
Step by Step Solution
★★★★★
3.26 Rating (170 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Activity Time ES EF LS LF Slack Critical A 6 0 6 2 8 2 No ... View full answer