Question: Develop MRP records for the items in Figure 7.16, Table 7.21, and Table 7.22. In figure 7.16 The lead time to complete item A is

Develop MRP records for the items in Figure 7.16, Table 7.21, and Table 7.22.
In figure 7.16
Develop MRP records for the items in Figure 7.16, Table
Develop MRP records for the items in Figure 7.16, Table

The lead time to complete item A is 2 weeks, and the lead time to complete item H is 1 week.

D (2) F C2) G (2) E ) 1(3) 10) TABLE 7.21 MS Finish Product 55 40 80 100 180 140 90 60 50 TABLE 7.22 Planning Data Data Category Lot size rule Lead time Safety stock Scheduled receipts Beginning inventory 141 LAL 2 weeks 15 None 30 1 week 25 None 400 2 weeks 35 800 1 week 2 weeks 1.300 week 1 1,200 week 1 week 1 20

Step by Step Solution

3.41 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

MRP records for items in Figure 76 Table 721 and Table 722 A H H A H 1 Item D Description Beg In... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

792-B-M-L-S-C-M (4575).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!