Question: Develop the material requirements plan for all components and intermediate items associated with product A for the next 10 weeks. Refer to Solved Problem 1
Develop the material requirements plan for all components and intermediate items associated with product A for the next 10 weeks. Refer to Solved Problem 1 (Figure) for the bill of materials and Table for component inventory record information. The MI’S for product A calls for 50 units to be started in weeks 2, 6, 8, and 9.
.png)
Inventory RecordData
item Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts Begining inventory F00 = 1 00 POO(P-2) 3 weeks L4L 6 weeks L4L 1 week L4L 2 waeks 30 150 (week 2) 30 LAL 3 weeks 10 50(week 2) 20 3 weeks 40 (week 3) None None 60 400 (week 6) 400
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
MRP for Fig Item Data Category B C D E F G Lotsize rule L4L L4L POQ P 2 L4L L4L FOQ 100 Lead time 2 weeks 3 weeks 3 weeks 6 weeks 1 week 3 weeks Safet... View full answer