The BOM for product A is shown in Figure. The MPS for product A calls for 120 units to be
Question:
The BOM for product A is shown in Figure. The MPS for product A calls for 120 units to be started in weeks 2, 4, 5, and 8. Table shows data from the inventory records. Develop the material requirements plan for the next 8 weeks for eachitem.
.png)