Question: The BOM for product A is shown in Figure. The MPS for product A calls for 120 units to be started in weeks 2, 4,

The BOM for product A is shown in Figure. The MPS for product A calls for 120 units to be started in weeks 2, 4, 5, and 8. Table shows data from the inventory records. Develop the material requirements plan for the next 8 weeks for eachitem.

The BOM for product A is shown in Figure. The

C3 B12 O (11 E0) INVENTORY RECORD DATA Item Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts 150 eek 2 450 (week 2) 700 (wee Beginning Inntory 125 L4L L4L 3 weeks FOQ 700 F00 700 L4L 3 weeks 4 weeks 2 weeks 1week 50 None 400 tweck t 235 750

Step by Step Solution

3.48 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

MRP for Fig Item Data Category B C D E F Lotsize rule L4L FOQ 700 FOQ 700 L4L L4L Lead time 3 weeks ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

227-B-M-L-S-C-M (1117).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!