Question: The BOM for product A is shown in Figure. The MPS for product A calls for 120 units to be started in weeks 2, 4,
The BOM for product A is shown in Figure. The MPS for product A calls for 120 units to be started in weeks 2, 4, 5, and 8. Table shows data from the inventory records. Develop the material requirements plan for the next 8 weeks for eachitem.
.png)
C3 B12 O (11 E0) INVENTORY RECORD DATA Item Data Category Lot-sizing rule Lead time Safety stock Scheduled receipts 150 eek 2 450 (week 2) 700 (wee Beginning Inntory 125 L4L L4L 3 weeks FOQ 700 F00 700 L4L 3 weeks 4 weeks 2 weeks 1week 50 None 400 tweck t 235 750
Step by Step Solution
3.48 Rating (168 Votes )
There are 3 Steps involved in it
MRP for Fig Item Data Category B C D E F Lotsize rule L4L FOQ 700 FOQ 700 L4L L4L Lead time 3 weeks ... View full answer