Question: LeBron Woods is responsible for developing a leadership - training program for his organization. The following table describes the relationships between the activities that need
LeBron Woods is responsible for developing a leadershiptraining program for
his organization. The following table describes the relationships between the
activities that need to be completed.
Activity
Days
Immediate Predecessors a m b
A
B
C A B
D C
E C
F E
G F
H D
I F H
J G I
Chapter :Project Management
a Determine the expected times and variances for each activity.
b Construct a project network for this problem.
c Determine the EST, EFT, LST LFT and slack for each activity. Also determine the critical path and project completion time.
d What is the probability that the project will be finished in less than
days?
e What is the probability that the project will need at least days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock