Question: LeBron Woods is responsible for developing a leadership - training program for his organization. The following table describes the relationships between the activities that need

LeBron Woods is responsible for developing a leadership-training program for
his organization. The following table describes the relationships between the
activities that need to be completed.
Activity
Days
Immediate Predecessors a m b
A 3714
B 51015
C 3510 A, B
D 51213 C
E 258 C
F 2514 E
G 5811 F
H 61014 D
I 348 F, H
J 4710 G, I
436Chapter 7:Project Management
(a) Determine the expected times and variances for each activity.
(b) Construct a project network for this problem.
(c) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the critical path and project completion time.
(d) What is the probability that the project will be finished in less than 49
days?
(e) What is the probability that the project will need at least 54 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!