Question: Lamont Henri needs to plan and manage a local construction project. The following table describes the relationships between the activities that need to be completed:

Lamont Henri needs to plan and manage a local construction project. The following table describes the relationships between the activities that need to be completed:
Lamont Henri needs to plan and manage a local construction

If using Crystal Ball, assume that the actual duration of each activity follows a BetaPert distribution, with the three time estimates shown for that activity. Otherwise, assume that each activity time is normally distributed with expected time and standard deviation computed as shown in equations 7-6 and 7-8, respectively, on page 283. Round off all activity times to one decimal place. Use simulation to determine the probability that the project will take at least 50 days.

DAYS IMMEDIATE m PREDECESSORS 8 13 ACTIVITY a 4 10 7 14 20 9 16 19 9 11 D, E C, F G, H

Step by Step Solution

3.37 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

718-M-S-L-P (1291).xlsx

300 KBs Excel File

Students Have Also Explored These Related Statistics Questions!