Question: For the network shown in Figure with all times indicating weeks, answer the following questions: a. What is the impact on the end date of
For the network shown in Figure with all times indicating weeks, answer the following questions:
a. What is the impact on the end date of the project if activity F slips by seven weeks?
.png)
b. What is the impact on the end date of the project if activity E slips by one week?
c. What is the impact on activity H if activity C were to slip by two weeks?
d. What is the impact on the end date of the project if activity B slips by twoweeks?
2 START FINISH 2
Step by Step Solution
3.35 Rating (173 Votes )
There are 3 Steps involved in it
Activity Early Start Early Finish Latest Start Latest Fin... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
93-B-M-L-P-M (843).docx
120 KBs Word File