Question: For the Soda Galore problem discussed in the chapter, assume that employees negotiate an increase in the regular production wage rate to $24.00 per hour
For the Soda Galore problem discussed in the chapter, assume that employees negotiate an increase in the regular production wage rate to $24.00 per hour and $36.00 per hour for overtime. Rework all aspects of the problem using the new wage rates.
Step by Step Solution
3.40 Rating (175 Votes )
There are 3 Steps involved in it
New Labor cost per case 160 hours 24hour 3840 38404000 cases 96 per case Level Production Plan Beginning inventory 5000 Beginning workers 8 Month Dema... View full answer