Question: Four samples (k = 4) are taken from a process, with each sample consisting of five observations (n = 5). The sampled items are subjected
Develop an R chart to determine if the dispersion is stable or not.
.png)
SampleObsObs2Obs3 Obs4 Obs5 125.99 118.14 125.81312122.41 115.47 115.56 114.80120.80123.13 139.48 117.53 130.8120.49108.22 125.50 141.03 121.64108.45109.18
Step by Step Solution
3.42 Rating (168 Votes )
There are 3 Steps involved in it
The process is stable because the sample ranges fall b... View full answer