Question: From an MTM synthesis, the standard time for one C-assembly is calculated to be 1.0 min? A new worker typically requires about 2 min. for

From an MTM synthesis, the standard time for one C-assembly is calculated to be 1.0 min? A new worker typically requires about 2 min. for the first assembly and drops to about 1.7 min. by the 5th assembly.
a) Calculate and plot the learning curve.
b) What is the % learning?
c) How long will it take the new worker to reach standard performance?