Question: Given the following network, (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be

Given the following network,


Given the following network,


(a) What is the critical path?
(b) How long will it take to complete this project?
(c) Can activity B be delayed without delaying the completion of the project? If so, how manydays?

D7 A8 G5 Start C3E6 End BIO F7 H3