Question: Given the following network, (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be
Given the following network,
.png)
(a) What is the critical path?
(b) How long will it take to complete this project?
(c) Can activity B be delayed without delaying the completion of the project? If so, how manydays?
D7 A8 G5 Start C3E6 End BIO F7 H3
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
Please see note about network depiction preceding Problem 1 a The critical path activitie... View full answer