Question: Given the following network (times are in weeks), determine: (a) The ES, LS, EF, and LF for each activity. (b) The slacks on all activities.
(a) The ES, LS, EF, and LF for each activity.
(b) The slacks on all activities.
(c) The critical activities andpath.
.png)
C7 H4 D2 E6 Start End B5 F4 G8
Step by Step Solution
3.52 Rating (162 Votes )
There are 3 Steps involved in it
Start 0 03 A 0 3 3 065 B 5 11 30 10 C 3 7 10 5 3 ... View full answer