Question: Given the following network (times are in weeks), determine: (a) The ES, LS, EF, and LF for each activity. (b) The slacks on all activities.

Given the following network (times are in weeks), determine:
(a) The ES, LS, EF, and LF for each activity.
(b) The slacks on all activities.
(c) The critical activities andpath.
Given the following network (times are in weeks), determine: (a)

C7 H4 D2 E6 Start End B5 F4 G8

Step by Step Solution

3.52 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Start 0 03 A 0 3 3 065 B 5 11 30 10 C 3 7 10 5 3 ... View full answer