Question: Given the schedule in Table B for a liability work package done as part of an accounting audit in a corporation, find: (a) The critical
(a) The critical path.
(b) The slack time on process confirmations.
(c) The slack time on test pension plan.
(d) The slack time on verify debt restrictioncompliance.
.png)
Duration Preceding (days) Activities Activity a. Obtain schedule of liabilities b. Mail confirmation c. Test pension plan d. Vouch selected liabilities e. Test accruals and amortization f Process confirmations g. Reconcile interest expense none 15 60 40 to debt h. Verify debt restriction 10 c, e compliance i. Investigate debit balances j. Review subsequent payments 12 h,i
Step by Step Solution
3.50 Rating (163 Votes )
There are 3 Steps involved in it
a The critical path is A D E G I J b The slack on process confirmation F is 20 days c The slac... View full answer