Question: How many of part J will be needed if 40 units of end item A are needed? Managers have decided to outsource part G. Revise

How many of part J will be needed if 40 units of end item A are needed? Managers have decided to outsource part G. Revise the BOM for end item A, assuming that item G is now purchased from a supplier. How many of part J will now be needed if 40 units of end item A are needed?

Step by Step Solution

3.47 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Part J is used in Components G and E 40 As x 2 Bs for each A 80 ... View full answer