In the project shown below, activities are represented by arrows, and the number for each activity also
Question:
a) Determine the critical path and the length of this project.
b) Assume that each activity, except 1 and 2, can be crashed up to 2 days at a cost equal to the activity number. E.g. activity 6 normally takes 6 days, but could be crashed to 5 days for a cost of $6, or to 4 days for a total of $12. Determine the least-cost 26-day schedule. Show the activities that are crashed and the total crash costs.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Niebels Methods, Standards and Work Design
ISBN: 978-0073376318
13th edition
Authors: Andris Freivalds, Benjamin Niebel
Question Posted: