In the project shown below, activities are represented by arrows, and the number for each activity also indicates its normal duration (in days).
a) Determine the critical path and the length of this project.
b) Assume that each activity, except 1 and 2, can be crashed up to 2 days at a cost equal to the activity number. E.g. activity 6 normally takes 6 days, but could be crashed to 5 days for a cost of $6, or to 4 days for a total of $12. Determine the least-cost 26-day schedule. Show the activities that are crashed and the total crash costs.
10

10

Step by Step Solution

3.52 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The critical path is shown in yellow and takes 30 weeks b Cras... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1439-B-H-R-M-E-R(249).docx

120 KBs Word File

Students Have Also Explored These Related Human Resource Management Questions!