Question: Table contains information about an environmental cleanup project. Shorten the project three weeks by finding the minimum cost schedule. Assume that project indirect costs and
Table contains information about an environmental cleanup project. Shorten the project three weeks by finding the minimum cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crashcosts.
.png)
ENVIRONMENTAL PROJECT DATA Immediate Predecessorts) Activity Normal Time (weeks) Crash Time (weeksCost to Crash (S per week) None 250 12 300 C D D,E 200 350
Step by Step Solution
3.42 Rating (168 Votes )
There are 3 Steps involved in it
AON Diagram for the environmental project Total crash costs 1... View full answer