Jana Crebs is a contractor for the construction of large office buildings. At the beginning of 2013,

Question:

Jana Crebs is a contractor for the construction of large office buildings. At the beginning of 2013, three buildings were in progress. The following data describe the status of these buildings at the beginning of the year:

Jana Crebs is a contractor for the construction of large

During 2013, the following costs were incurred.
Building 1 $930,000 (estimated cost to complete as of December 31, 2013, $750,000)
Building 2 $1,800,000 (job completed)
Building 3 $7,400,000 (estimated cost to complete as of December 31, 2013, $2,800,000)
Building 4 $800,000 (contract price, $2,500,000; estimated cost to complete as of December 31, 2013, $1,200,000)
Instructions:
1. Compute the total revenue, costs, and gross profit in 2013. Assume that Crebs uses the cost-to-cost percentage-of-completion method. (Note: Round percentage to two decimal places for percentage completed.)
2. Compute the gross profit for 2013 if Crebs uses the completed-contract method.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting

ISBN: 978-0538479738

18th edition

Authors: Earl K. Stice, James D. Stice

Question Posted: