Question: The expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 6. What is the probability

The expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 6. What is the probability that the project will require

A. Require at least 17 months

B. Be completed in 20 months

C. Require at least 23 months?

D. Be completed within 25 months?

Use excel QM / Pom for excel please to show work.

Step by Step Solution

3.43 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Normal Distribution Mean u 21 Standard Deviation sd245 Normal Dis... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-A-C-A (1819).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!