Question: Jim (Problem) has just determined that both Activity D and Activity I have been completed. What is the impact of this on the critical path

Jim (Problem) has just determined that both Activity D and Activity I have been completed. What is the impact of this on the critical path and the total project completion time?

Step by Step Solution

3.36 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The results of having both activity D 4 and I 9 completed are shown in ... View full answer