Question: Jobs A, B, C, and D must be processed through the same machine center. Sequence the following jobs by (a) SPT (b) SLACK. Calculate mean
(a) SPT
(b) SLACK.
Calculate mean flow time, mean tardiness, and maximum tardiness. Which sequencing rule would you recommend?Why?
.png)
Job Processing Time Due Date 20 10 30 15 20 15 50 30
Step by Step Solution
3.34 Rating (166 Votes )
There are 3 Steps involved in it
a SPT Processing Job time Duedate B 10 15 D 15 30 A 20 20 C 30 50 Start Proc... View full answer