Question: Sequence the following jobs by (a) SPT (b) DDATE (c) SLACK. Calculate mean flow time, mean tardiness, and maximum tardiness. Which sequencing rule would you
Sequence the following jobs by
(a) SPT
(b) DDATE
(c) SLACK.
Calculate mean flow time, mean tardiness, and maximum tardiness. Which sequencing rule would you recommend?Why?
(a) SPT
(b) DDATE
(c) SLACK.
Calculate mean flow time, mean tardiness, and maximum tardiness. Which sequencing rule would you recommend?Why?
.png)
Job Processing Time Due Date 18
Step by Step Solution
★★★★★
3.40 Rating (175 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
a SPT Processing Job time Duedate B 3 5 A 5 8 D 6 7 C 9 18 Start Processing Completion Job time time ... View full answer