MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was

Question:

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows:

___________________________________________ 2019 ______________2020__

Costs incurred during the year.................$290,000................$150,000

Estimated additional cost to complete.....145,000........................     -

Billings during the year................................260,000..................265,000

Cash collections during the year................240,000..................285,000


Required:

1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.

2. Record the preceding transactions in MSK's books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial Reporting and Analysis

ISBN: 978-1259722653

7th edition

Authors: Lawrence Revsine, Daniel Collins, Bruce Johnson, Fred Mittelstaedt, Leonard Soffer

Question Posted: