MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was
Question:
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows:
___________________________________________ 2019 ______________2020__
Costs incurred during the year.................$290,000................$150,000
Estimated additional cost to complete.....145,000........................ -
Billings during the year................................260,000..................265,000
Cash collections during the year................240,000..................285,000
Required:
1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied.
2. Record the preceding transactions in MSK's books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.
Step by Step Answer:
Financial Reporting and Analysis
ISBN: 978-1259722653
7th edition