Question: 1. When would the project be completed using the normal durations? 2. Is it possible to complete the project in 18 weeks? What would the
1. When would the project be completed using the normal durations?
2. Is it possible to complete the project in 18 weeks? What would the associated additional cost be? Which activities would need to be completed on a crash basis?
3. Is there some time frame shorter than the 18 weeks Vera has recommended that would make more sense in terms of profits?
The Fantasy Products Company (disguised name) is a manufacturer of high-quality small appliances intended for home use. The company€™s current product line includes irons, a small hand-held vacuum, and a number of kitchen appliances such as toasters, blenders, waffle irons, and coffeemakers. Fantasy Products has a strong R&D department that continually searches for ways to improve existing products as well as developing new ones.
Currently, the R&D department is working on the development of a new kitchen appliance that will chill foods quickly much as a microwave oven heats them quickly, although the technology involved is quite different. Tentatively named The Big Chill, the product will initially carry a price tag of around $125, and tire target market consists of upper- income consumers. At this price, it is expected to be a very profitable item. R&D engineers now have a working prototype and are satisfied that, with the cooperation from the production and marketing people, tire product can be ready in time for the all-important Christmas buying season. A target date has been set for product introduction that is 24 weeks away.
-1.png)
-2.png)
Table 1 list of activities involved in product introduction and precedence relationships Aetivity Doseription Immediato Predecossor(s) Select and crder production equipment Receive production equipment from supplier Install and set up production equipment Finalize bill of material Order parts Receive parts First producton run Finclize marketing pian Produce magczine ads Script for TV ads Produce TV ads Bogin ad campaign Ship product to consumers Table 2 Duration and cost esf males for initroduction of The Big Chill Normal Duration (weeks) Crash Duration (weeks) Normal & Crash Cost $4,400 12,000 7,000 2,000 3,000 Activity Norml Cost $2,000 9,000 2,000 1,000 2,000 12,000 3,500 5,000 8,000 50,000 10,000 5,000 24,000 8,000 8,000 15,000 70,000 10,000 5,000 4
Step by Step Solution
3.48 Rating (174 Votes )
There are 3 Steps involved in it
1 First draw the precedence network diagram Path duration ABCGM 22 DEFGM 16 HILM 15 HJKLM 18 Using n... View full answer