Question: Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In
Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take,
-1.png)
Their responses shown in the following table
-2.png)
a. What is the expected completion time of the project?
b. What is the probability of completing the project in 21 days?
c. What is the probability of completing the project in 17 days?
Start Finish Time Estimates (days) Activity OptimisticMost Likely Pessimistic 10
Step by Step Solution
3.36 Rating (174 Votes )
There are 3 Steps involved in it
a The expected activity times in days are The critical path is ADE because it ... View full answer