Recently, you were assigned to manage a project for your company. You have constructed a network diagram

Question:

Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take,

Recently, you were assigned to manage a project for your


Their responses shown in the following table

Recently, you were assigned to manage a project for your


a. What is the expected completion time of the project?
b. What is the probability of completing the project in 21 days?
c. What is the probability of completing the project in 17 days?