Recently, you were assigned to manage a project for your company. You have constructed a network diagram
Question:
Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take,
Their responses shown in the following table
a. What is the expected completion time of the project?
b. What is the probability of completing the project in 21 days?
c. What is the probability of completing the project in 17 days?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations management processes and supply chain
ISBN: 978-0136065760
9th edition
Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra
Question Posted: