Question: Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In

Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project. In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take,

Recently, you were assigned to manage a project for your


Their responses shown in the following table

Recently, you were assigned to manage a project for your


a. What is the expected completion time of the project?
b. What is the probability of completing the project in 21 days?
c. What is the probability of completing the project in 17 days?

Start Finish Time Estimates (days) Activity OptimisticMost Likely Pessimistic 10

Step by Step Solution

3.36 Rating (174 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The expected activity times in days are The critical path is ADE because it ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

227-B-M-L-O-M (905).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!