Question: In solved problem, estimates the probability that the noncritical path B-F-G-will take more than 20 weeks.
In solved problem, estimates the probability that the noncritical path B-F-G-will take more than 20 weeks.
Step by Step Solution
3.45 Rating (174 Votes )
There are 3 Steps involved in it
Where T 20 weeks T E 55 90 45 19 weeks and the sum of the varia... View full answer