Which of the following is the planning technique that identifies implementation activities and their relationships, constructs a
Question:
Which of the following is the planning technique that identifies implementation activities and their relationships, constructs a network of arrows and nodes, and then determines the critical path through the network?
a. Gantt chart
b. PERT diagram
c. Physical model
d. Data flow diagram