Question: A project manager is managing a project and is considering the reschedule of an activity because one of the project engineers must work on this

A project manager is managing a project and is considering the reschedule of an activity because one of the project engineers must work on this activity and another activity at the same time. Each of the activities is scheduled to have a duration of two weeks. One of the activities is on the critical path and the other activity has eighteen days of free float.

The project manager should:

a. Reschedule the activity that has no float.

b. Reschedule the activity with float.

c. Ask the engineer to work overtime.

d. Reschedule both activities to take advantage of the float on each.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!