Question: The program evaluation and review technique (PERT) method of scheduling differs from the critical path method (CPM) because the PERT method: a. Uses weighted averages

The program evaluation and review technique (PERT) method of scheduling differs from the critical path method (CPM) because the PERT method:

a. Uses weighted averages of activity durations to calculate project duration.

b. Uses ‘‘dummy’’ activities to represent logic ties.

c. Uses ‘‘free float’’ instead of ‘‘total float’’ in the schedule calculations.

d. Uses bar charts instead of logic diagrams to portray the schedule.