A project manager is managing a project working to produce a fitness tracking device.
Using an adaptive approach to managing the schedule, the project manager works with the team to update and prepare stories for the upcoming iteration, accounting for any recent changes that may have occurred. This is an example of:
A. Backlog refinement B. Schedule management C. Project management D. Sprint planning