Question: A small sample of your projects critical path is shown in the following table. Assuming each activity must finish before the next activity can begin,

A small sample of your project’s critical path is shown in the following table. Assuming each activity must finish before the next activity can begin, what is the late start and late finish date for activity 3?Activity Duration Early Start Early Finish 1 22 5/1 5/22 2 5

A. Late start is 5/30, and late finish is 6/5.
B. Late start is 5/29, and late finish is 6/4.
C. Late start is 5/31, and late finish is 6/6.
D. Late start is 6/5, and late finish is 6/11.

Activity Duration Early Start Early Finish 1 22 5/1 5/22 2 5 5/23 5/28 3 7 5/29 6/4 4 1 615 6/5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!