Question: A small sample of your projects critical path is shown in the following table. Assuming each activity must finish before the next activity can begin,
A small sample of your project’s critical path is shown in the following table. Assuming each activity must finish before the next activity can begin, what is the late start and late finish date for activity 3?
A. Late start is 5/30, and late finish is 6/5.
B. Late start is 5/29, and late finish is 6/4.
C. Late start is 5/31, and late finish is 6/6.
D. Late start is 6/5, and late finish is 6/11.
Activity Duration Early Start Early Finish 1 22 5/1 5/22 2 5 5/23 5/28 3 7 5/29 6/4 4 1 615 6/5