Question: A small sample of your projects critical path is shown in the following table. Assuming each activity must finish before the next activity can begin,

A small sample of your project’s critical path is shown in the following table. Assuming each activity must finish before the next activity can begin, which of the following options is not correct?Activity Duration Early Start Early Finish 1 22 5/1 5/22 2 5

A. Activity 1-2-3-4 is the critical path.
B. Late start and late finish are the next set of calculations to perform.
C. To complete the chart and determine the remaining dates for activity 4, you have to perform a backward pass.
D. After early start, early finish, late start, and late finish dates are established, you can calculate the float for each activity.

Activity Duration Early Start Early Finish 1 22 5/1 5/22 2 5 5/23 5/28 3 7 5/29 6/4 4 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!