Question: Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She is currently facilitating the estimating
Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She is currently facilitating the estimating process to calculate the duration of the project’s activities. Alyssa knows that she has reliable information and is therefore planning on using an estimating technique that will yield a highly accurate estimate with minimal effort expended. What estimating technique is she planning on using?
A. Three-point estimating B. Bottom-up estimating C. Parametric estimating D. Top-down estimating