Question: Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She updates a stakeholder engagement matrix
Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She updates a stakeholder engagement matrix that she created at the start of the project to document the communication needs of the project.
What tool or technique is Alyssa using?
A. Project management information system B. Interpersonal and team skills C. Expert judgment D. Data representation