Question: Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She has used a waterfall approach

Alyssa is a project manager tasked with managing an infrastructure project that will consolidate five data centers into one. She has used a waterfall approach to carry out initial planning activities and is executing the work using an Agile-based approach. She shows the team how much work remains to be completed during their current iteration and the forecast of work to be completed for the remaining iterations based on existing velocity. What is Alyssa showing them?

A. Schedule B. Burnup chart C. Milestone chart D. Burndown chart