Question: Diana is a project manager for a small technology startup. One of her first projects involves shifting data hosting from an on-premise solution to a
Diana is a project manager for a small technology startup. One of her first projects involves shifting data hosting from an on-premise solution to a cloud-based one. With work now fully underway, she begins generating status reports so that they can later be distributed to the project team and other relevant stakeholders. Which process group does this activity—creation of status reports—belong to?
A. Planning B. Executing C. Monitoring and Controlling D. Closing