Find the labor cost, including overhead and profit for the formwork for 48 columns of 24
Question:
Find the labor cost, including overhead and profit for the formwork for 48 columns of 24ʺ × 24ʺ × 9ʹ. Use the data shown in Figure 17.7.
Figure 17.7
Transcribed Image Text:
03 11 13 Concrete Forming 13.25 FORMS IN PLACE, COLUMNS 6500 24" X 24" plywood columns, 1 use General work description Crew No. Crew C-1 3 Carpenters 1 Laborer 32 L.H. Daily Total Hr. 38.10 30.25 Line item determination: Major UCI subdivision = 03.11 Major classification within subdivision 13.25 Line item number = 6500 Complete line number: 03 11 13.25 6500 CREW C-1 Crew C-1 Bare Costs DAILY OUTPUT 190 $1156.40 UNIT S.F.C.A 2.64 Square Foot Contact Area Incl. Subs O&P Daily Hr. 914.40 59.30 242.00 47.05 BARE COSTS MAT. INST. TOTAL 6.10 Daily 1423.20 376.40 $ 1799.60 (These figures are printed above) BARE COSTS are developed as follows: MAT. is 2.64/SFCA INST. Crew C-1 Daily Bare Cost = 1156.40 Daily Output 190 8.74 $6.10/SFCA (rounded) TOTAL = MAT. + INST. = $2.64+ $6.10= $8.74per S.F.C.A. TOTAL INCL. O&P 12.35 (Only the total of these figures is printed above) TOTAL COSTS INCL. O&P are developed as follows. MAT. is BARE MAT. + 10% = 2.64 +0.26 = $2.90/SFCA 190 INST. Crew C-1 Daily Bare Cost = $ 1799.60.9.45/SFCA Daily Output (rounded) TOTALMAT.+ INST. = $2.90+ $9.45 $12.35/SFCA
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (2 reviews)
Answered By
Muhammad Umair
I have done job as Embedded System Engineer for just four months but after it i have decided to open my own lab and to work on projects that i can launch my own product in market. I work on different softwares like Proteus, Mikroc to program Embedded Systems. My basic work is on Embedded Systems. I have skills in Autocad, Proteus, C++, C programming and i love to share these skills to other to enhance my knowledge too.
3.50+
1+ Reviews
10+ Question Solved
Related Book For
Construction Management
ISBN: 9781119256809
5th Edition
Authors: Daniel W. Halpin, Bolivar A. Senior, Gunnar Lucko
Question Posted:
Students also viewed these Business questions
-
Revise the cost for the formwork for the columns of problem 17.6 if the carpenters earn $42.00/hr. Problem 17.6 Find the labor cost, including overhead and profit for the formwork for 48 columns of...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-6. On December 12, Irene purchased the building where her store is located. She paid...
-
Carol Harris, Ph.D, CPA, is a single taxpayer and she lives at 674 Yankee Street, Durham, NC 27409. Her Social Security number is 793-52-4335. Carol is an Associate Professor of Accounting at a local...
-
According to Dr. Grant, creatives are people who ________. A. Are procrastinators B. Act on multiple ideas C. Plan out each detail D. Are highly confident with no doubts about their success
-
Under what conditions would you be a long hedger in financial futures? A short hedger?
-
Suppose the bottom of the infinite square well is not flat ( V (x) =0), but rather Use the method of Problem 2.61 to find the three lowest allowed energies numerically, and plot the associated wave...
-
These data consist of the 503 daily returns for the calendar years 2005 and 2006 of the S\&P value-weighted index. (The data file contains additional years - this exercise uses only 2005 and 2006...
-
David Lemay is the chief executive officer of Brenna Electronics. Lemay is an expert engineer but a novice in accounting. Lemay asks you, as an accounting student, to explain (a) the bases for...
-
Please show me the Calculation step by step. Thank you Financial Analysis : Facts: $1 US = $1.40 CDN One truckload / container = 1940 cases One truckload / container = 25 standard pallets One pallet...
-
As a construction project manager, what general categories of information would you want to have on a cost control report to properly evaluate what you think is a developing overrun on an operation,...
-
Given the bridge abutment shown here, determine the number of worker hours required to form the structure using data from R. S. Means or other appropriate reference. 30' 50' 1 30' 8'
-
Microserve provides computer repair service on a contract basis to customers in five sections of the city. The five sections, the number of service contracts in each section, and the x, y coordinates...
-
Describe the procedures you would develop to liaise with educators, learners, and others to monitor learning and development strategies and relevant resources.
-
At UPS, what performance measures receive the greatest focus/attention. How valuable and effective are these measures for guiding and directing the business? Would you recommend any change relative...
-
How could you analyze and align organizational learning strategy with HR (human resources) requirements?
-
What attributes and characteristics distinguish an effective manager, encompassing a spectrum of competencies, leadership styles, and strategic acumen essential for navigating the complexities of...
-
What are examples of forensic document examination comparisons?
-
Lien Company engaged in the following transactions: July 2 Purchased merchandise on credit from Jonak Company, terms 2/10, n/30, FOB destination, invoice dated July, 1, $4,000. 6 Returned some...
-
The following table shows the rates of total return in successive years from 2004 to 2008 for the Sprott Canadian Equity Fund and for the benchmark Toronto Stock Exchange S&P/TSX Composite Index. By...
-
The first progress payment received by the contractor is signified by the first vertical segment of the income curve in Figures 4.1, 4.2, and 4.3. Why is this first payment shown at the end of the...
-
Visit a local contractor and determine the proportion of contracts that are negotiated against those that are competitively bid awards. Is this percentage likely to change significantly with small...
-
From the point of view of the owners contract administrator, each different type of contract places different demands on supervision. List the significant differences that would impact the complement...
-
A public golf course has about 100 golfers per day and charges each golfer $15 to play. The golf course owner predicts that there will be 10 more golfers each day for every $1 reduction in the price...
-
Nintendo's main hardware product is the Switch, a portable and affordable video game console for casual gaming. Which of these is NOT a likely reason Nintendo would want to launch a more expensive,...
-
1) Describe operating leverage. Explain why the overestimation of sales has a more serious effect on project valuation in case of a project with high operating leverage! provide an example. Provide...
Study smarter with the SolutionInn App