Question: Mike is a project manager for an IT technology implementation project. He is using an Ishikawa diagram to figure out what could cause potential risks
Mike is a project manager for an IT technology implementation project. He is using an Ishikawa diagram to figure out what could cause potential risks on his project. Which process is he doing?
A. Identify Risks B. Perform Qualitative Risk Analysis C. Perform Quality Control D. Plan Risk Responses