Question: Suppose five activities are on a CPM critical path and each activity has TS = 2. Determine the overall effect on the critical path length

Suppose five activities are on a CPM critical path and each activity has TS = 2.

Determine the overall effect on the critical path length if two of the critical activities are delayed by 2 time units each. Discuss.