Question: The original schedule (for a project, a work package, or an activity), plus or minus approved changes, is called: a. The working schedule. b. The

The original schedule (for a project, a work package, or an activity), plus or minus approved changes, is called:

a. The working schedule.

b. The target schedule.

c. The performance schedule.

d. The baseline schedule.