Question: The Program Evaluation and Review Technique (PERT) method of scheduling differs from the Critical Path Method (CPM) because the PERT method uses: a. Weighted averages
The Program Evaluation and Review Technique (PERT) method of scheduling differs from the Critical Path Method (CPM) because the PERT method uses:
a. Weighted averages of activity durations to calculate the project duration.
b. Dummy activities to represent logic ties.
c. Free Float instead of total float in the schedule calculation.
d. Bar Charts instead of diagrams to portray the schedule.
e. Segmented network logic