Question: The project processes are iterative, are results oriented, and interact with each other. Shewhart and Deming developed a concept that reflects this idea. Which of
The project processes are iterative, are results oriented, and interact with each other.
Shewhart and Deming developed a concept that reflects this idea. Which of the following is the name of this cycle?
A. Plan-Do-Check-Act B. Initiate-Requirements-Execute-Close C. Select-Plan-Monitor-Act D. Strategize-Justify-Choose-Execute-Control