Question: The requirements for systems analysts and programmers for the GUMBY project are as follows: a. Compute ESs, LSs, and total slack times. b. Then show

The requirements for systems analysts and programmers for the GUMBY project are as follows:J M Activity Predecessors Duration (weeks) Systems Analysts (weekly) Programmers (weekly) 1454

a. Compute ESs, LSs, and total slack times.

b. Then show the separate resource loadings for systems analysts and programmers, assuming early start times.

c. Suppose the maximum weekly availability is eight systems analysts and fi ve programmers. Can activities be scheduled to satisfy these constraints without delaying the project?

J M Activity Predecessors Duration (weeks) Systems Analysts (weekly) Programmers (weekly) 1454 - 683 4 Y 1823 1253 L Q Z OL832 Y,Q N1253 VM632

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!