Question: The requirements for systems analysts and programmers for the GUMBY project are as follows: a. Compute ESs, LSs, and total slack times. b. Then show
The requirements for systems analysts and programmers for the GUMBY project are as follows:
a. Compute ESs, LSs, and total slack times.
b. Then show the separate resource loadings for systems analysts and programmers, assuming early start times.
c. Suppose the maximum weekly availability is eight systems analysts and fi ve programmers. Can activities be scheduled to satisfy these constraints without delaying the project?
J M Activity Predecessors Duration (weeks) Systems Analysts (weekly) Programmers (weekly) 1454 - 683 4 Y 1823 1253 L Q Z OL832 Y,Q N1253 VM632
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
