Question: The network and associated requirements for systems analysts and programmers for the GUMBY project are as follows: (a) Draw the network. Compute ESs, LSs, and

The network and associated requirements for systems analysts and programmers for the GUMBY project are as follows:N L Q L 8183 125 782 J M V Y V

(a) Draw the network. Compute ESs, LSs, and total slack times.

(b) Then show the separate resource loadings for systems analysts and programmers, assuming ESs.

(c) Suppose the maximum weekly availability is eight systems analysts and five programmers. Can activities be scheduled to satisfy these constraints without delaying the project?

N L Q L 8183 125 782 J M V Y V M 6 3 Y,Q 125 3 4 2 3 3 2 3 945 168 Activity Predecessors Duration (weeks) Systems Analysts (weekly) Programmers (weekly)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related MegaProject Management Questions!