Question: Use the minimum total slack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.
Use the minimum total slack (Min TS) heuristic to schedule the resource-constrained project. If a tie occurs, use minimum activity duration to break the tie.
Units of resource type 1 available = 10 Units of resource type 2 available = 15
Resource Units Activity Predecessor a M b Type 1 Type 2 A B C 52 1 2 4 6 4 +3 4254753 0 4 1 0 372 3542426 D A 1 3 4 E 4 5 F A 3 G B, D, E 1 +2 4 5 6 2