Question: Using the information displayed in the following table, identify the near critical path. A. A-B-E B. A-C-E C. A-D-E D. A-E-D Activity Name Successor Duration
Using the information displayed in the following table, identify the near critical path.
A. A-B-E B. A-C-E C. A-D-E D. A-E-D
Activity Name Successor Duration 5 A B, C, D B E C E D E 227 10 E None 2