Question: A project manager has just learned that the schedule performance index (SPI) for their project is 85 percent. The calculation of the cost performance index
A project manager has just learned that the schedule performance index (SPI) for their project is 85 percent. The calculation of the cost performance index (CPI) is 107 percent. How would you describe this project both in terms of budget and schedule?
Step by Step Solution
There are 3 Steps involved in it
Based on the provided SPI and CPI values the project can be described as follows Schedule Performanc... View full answer